| Change Management Schedule | ||||||||||||||||||||||
| Labor Day Weekend | ||||||||||||||||||||||
| Request # | Date / Time | Description / Originator | Affects / Impacts | |||||||||||||||||||
| 3446 (PT. 1) | Aug 27, 09:00 - N/A | Shutdown and relocate the
following Solaris Unix servers in building 9 and move them to the new Hot
Site: PENCE, GLADE, TEOCALLI, BULLION, ALTA, AJAX, STAR, and WESTON (SN6000) / Murphy |
Reboots MAY be required to re-attach server to drives. Emergency requests will be issued as needed. They will be done late Monday night if needed. AJAX will point to NEEDLE alias during this time. | |||||||||||||||||||
| 3557- 3559 | Aug 31, 18:00 - 3 Days | Breaking mirror on NIMBUS, STRATUS and NISA in
building 9, to move to the new hot site.
/ Murphy |
This change is in conjunction with the move of all servers in bldg 9 RESS to the new Hot Site. (REQ 3443) | |||||||||||||||||||
| 3446 (PT. 2) | Aug 31, 18:00 - 3 days | Shutdown and relocate the
following Solaris Unix servers in building 9 and move them to the new Hot
Site: ASCELLA, BTSRV2, ORNO, ARAPAHO, ARIKAREE, BLANC, KIOWA, LONGS, and CEREBRUS. / Murphy |
These Services will be totally
down: All Development Databases, Application Development and Info Warehouse Development. Limited impact to: Netbackup, NIS, and Printing |
|||||||||||||||||||
| 3443 | Aug 31, 18:00 - 3 Days | Shutdown and relocate the
following SAP HP servers in bldg 9 and move them to the new Hot Site: PINATUBO, DENALI, BELFORD, DOLLAR, KRAKATOA, PYRAMID, HAGUES, HURON and BALDY. / Bailey |
SAP QAS (test), DVL (development), TRN (training), TRG, CON and clarify Test will be unavailable. | |||||||||||||||||||
| 3442 | Aug 31, 16:00 - N/A | Turn off mirroring of the Production Clarify database on FLATTOP in bldg 9 while the mirror arrays and associated SAN switches are moved to the new Hot Site. / Bailey | No impact. We just won't have a mirror copy of the Clarify database until the move is complete and the mirroring is re-implemented. | |||||||||||||||||||
| 3441 | Aug 31, 16:00 - N/A | Turn off mirroring of the SAP production database on HANDIES in bldg 9 while the mirror arrays and associated SAN switches are moved to the new Hot Site. / Bailey | No impact. We just won't have a mirror copy of the sap production database. | |||||||||||||||||||
| 2902 | Aug 31,18:30 - 19:00 | CICS (CIPRD400 and CIPRD500) will be disabled and no longer available. / Kazmierski | CIPRD400 and CIPRD500 will be gone. | |||||||||||||||||||
| 2903 | Aug 31,18:30 - 19:00 | FOCUS will be disabled on the PRODUCTION LPAR and available on the OPEN LPAR. / Kazmierski | FOCUS will no longer be avaiable on the Production LPAR. | |||||||||||||||||||
| 3433 | Sept 01, 08:00 - 10:00 | Convert PINATUBO over to Gigabit Ethernet. Turn off ATM. / Bailey |
SAP QAS Database will be unavailable all weekend while all servers in bldg 9 are moved to the new Hot Site. (REQ 3443) | |||||||||||||||||||
| 3434 | Sept 01, 08:00 - 10:00 | Convert SAP Development Database server DENALI over to Gigabit Ethernet. Turn off ATM. / Bailey | SAP DVL Development Database will be unavailable all weekend while all servers in bldg 9 are moved to the new Hot Site. (REQ 3443) | |||||||||||||||||||
| 3435 | Sept 01, 08:00 - 10:00 | Convert SAP Production Application server BELFORD over to Gigabit Ethernet. Turn off ATM. Install Gigabit Ethernet card, drivers and June 2001 Extension software on BELFORD. / Bailey . / Bailey | Workload will be moved to other SAP Production Application servers in bldg 4. This change is in conjunction with the move of all servers in bldg 9 RESS to the new Hot Site. (REQ 3443) | |||||||||||||||||||
| 3436 | Sept 01, 08:00 - 10:00 | Convert SAP Production Application server HURON over to Gigabit Ethernet. Turn off ATM. Install Gigabit Ethernet card, drivers and June 2001 Extension software on HURON. / Bailey | Workload will be moved to other SAP Production Application servers in bldg 4. This change is in conjunction with the move of all servers in bldg 9 RESS to the new Hot Site. (REQ 3443) | |||||||||||||||||||
| 3437 | Sept 01, 08:00 - 10:00 | Convert SAP Production Application server HAGUES over to Gigabit Ethernet. turn off ATM. / Bailey | Workload will be moved to other
SAP Production Application servers in bldg 4. This change is in conjunction with the move of all servers in
bldg 9 RESS to the new Hot Site. |
|||||||||||||||||||
| 3438 | Sept 01, 08:00 - 10:00 | Convert SAP TRG Database server DOLLAR over to Gigabit Ethernet.Turn off ATM. / Bailey | SAP TRG database in bldg 9 will
be unavailable. This change is in
conjunction with the move of all servers in bldg 9 RESS to the new Hot Site
on Labor Day Weekend. (REQ 3443) |
|||||||||||||||||||
| 3439 | Sept 01, 08:00 - 10:00 | Convert SAP CON Database server KRAKATOA in bldg 9 over to Gigabit Ethernet. Turn off ATM. / Bailey | SAP CON database in bldg 9 will
be unavailable. This change is in
conjunction with the move of all servers in bldg 9 RESS to the new Hot Site
on Labor Day Weekend. (REQ 3443) |
|||||||||||||||||||
| 3440 | Sept 01, 08:00 - 10:00 | Convert Clarify Test Database server PYRAMID in bldg 9 over to Gigabit Ethernet. Turn off ATM. / Bailey | Clarify Test database in bldg 9 will be unavailable. This change is in conjunction with the move of all servers in bldg 9 RESS to the new Hot Site on Labor Day Weekend. | |||||||||||||||||||
| 3554 | Sept 02, 08:00 - 11:00 | Requesting IPL for the Production CCSMVS system to put maintenance on a few third party products in preparation for the upgrade from 2.6 to 2.10 which takes place on 09/14. . | The Production CCSMVS system will be unavailable along with all it's database's and application's during this outage. | |||||||||||||||||||
| 2901 | Sept 14,18:00 - 22:00 | Requesting IPL for the Production CCSMVS system to upgrade from 2.6 to 2.10. / Kazmierski | The Production CCSMVS system will be unvailable along with all it's application's during this outage. | |||||||||||||||||||